Decision details
The Transformation of Armada Way
Decision Maker: Delegated Decisions, Cabinet
Decision status: Recommendations approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
To respond to the decision of Cabinet on 19
February 2024 (Minute 117 refers).
Decision:
Cabinet:
1. Approved the final construction cost for the approved Armada Way design as £29,892,665;
2. Recommended the Leader approves additions to the Capital Programme as set out in the report giving a maximum spend allocation of £29,892,665 to finance the construction of the approved Armada Way scheme;
3. Noted that to support the on-going maintenance of projects within the city centre for a period of five years starting in 2025/2026 that hard and soft landscaping maintenance be funded from previously identified capital approved resources already forming part of the Capital Programme;
4. Granted authority to the Service Director for Strategic Planning and Infrastructure to take all such action as necessary to implement the project including all subsequent design amendments (excluding amendments which impact on the retention of any existing trees or the approved translocation of trees), scheme approval submissions, procurement and contract awards associated with developing and delivering the Armada Way scheme through to construction and completion, in consultation with the relevant Cabinet Members;
5. Delegated to the Cabinet Member for Finance authority to make any decisions which impact on the retention of any existing trees, or the approved translocation of trees associated with developing and delivering the Armada Way scheme through to construction and completion.
Publication date: 10/09/2024
Date of decision: 09/09/2024
Decided at meeting: 09/09/2024 - Cabinet
Effective from: 18/09/2024