Agenda item
CONTRACTOR UPDATE ON FACILITY PERFORMANCE, COMMUNITY INTERFACE AND UK BUSINESS
To receive a presentation from Mike Turner; MVV Managing Director and Jade Beavan; MVV Community Liaison Manager summarising the performance of the contract, facility and MVV’s business performance.
Minutes:
Mike Turner (MVV Managing Director) provided an update and highlighted the following for 2023/24:
a)
2023/24 had been a positive year overall with
greater than designed availability, increased carbon savings and
minimal public complaints;
b)
The summer 2023 open day has resulted in over 2000
visitors on site;
c)
Some long outages had affected throughput, but
overall had been a good year for availability so the electricity
generated and heat exported had been as high as they could
be;
d)
The heat exported had been lower than previous years
due to a health and safety issues with the heating system at the
dockyard;
e)
Availability was very good and above national
average;
f)
CO2eq saving was 92,547 tonnes, higher
than the previous three years and above target;
g)
There had been less unplanned shutdowns than in the
previous years, two due to tube leaks and one relating to a grate
fault;
h)
There had been one justified complaint in 2023/24
and was due to gas monitors being triggered during works and vents
automatically opening;
i.
Two further complaints had been attributed to other
facilities;
i)
Waste diversion was above target at
99.99%;
j)
Performance deductions had been applied;
i.
There were breaches in relation to delivery
turnaround times of 0.1%;
ii.
There had been 279 breaches in relation to waste
acceptance protocol due to human error
when initially inputting a registration and mistaking the letter X
for the letter K, which then went unnoticed. ANPR is being
installed to remove the risk of errors like this in
future;
iii.
One complaint had not been logged within timeframe,
and one outage had not been reported within timeframe;
k)
Signage upgrades to incorporate the new logo and
changed to PPE (Mandatory eye protection introduced);
l)
A new ladder inspection regime had been
introduced;
m)
New fire hose reels had been fitted and the fire
system had been upgraded;
n) The Cardox online high pressured blockage cleaning system had been introduced under trial.
Jade Beavan (MVV Community Liaison Manager) added the following in relation to community engagement:
o)
Reinforcement of the waste hierarchy and supported
delivery of Partner Council’s key waste minimisation
messages;
p)
Facilitated tours and careers Q&A
sessions;
q)
Organised and attended local events;
r)
Participated in waste education meetings and hosted
partner site tours and waste education visits;
s)
The decrease in hours spent with schools was likely
due to the cost of transport for schools to get to the
facility;
t)
Outreach offerings had increased;
u)
Usage of visitor centre had increased, particularly
with Plymouth schools, which Jade had been working hard
on;
v)
There had not been any interest in virtual tours
since the conclusion of the COVID19 pandemic;
w)
The open day in 2023 had seen very high visitor
numbers at approximiately 2000, and whilst 2024 was lower at 350,
it was more manageable;
i.
All Council partners had attended the
event;
ii.
Interest in bookings had increased after the
event.
Mike Turner (MVV Managing Director) added:
x)
A development in Medworth, Cambridgeshire, a site
twice the size of Plymouth, had planning permission and EfW (Energy
from Waste) construction was expected to commence in July
2025;
i.
Waste contracts had already been sold;
ii.
It would provide steam and power in the area and was
carbon capture ready;
iii.
It was expected to open in 2028;
y)
Another project in Canford, Bournemouth, similar to
Plymouth’s facility, had been delayed in going to Planning
Committee, but was expected to do so before the end of 2024 and EfW
construction was expected to begin in 2026/27;
z)
In Germany, MVV continued to have a number of green
projects including a heat pump in Mannheim that was providing green
heating to 3500 local homes;
aa) MVV was a local authority owned company in Mannheim.
In response to questions it was further discussed:
bb) In order to try and help
schools with the cost of transport, MVV had increased the number of
children in a tour, allowing more than one class to attend and
making it more cost effective;
cc)
Concerns over lower attendance from Devon County
Council schools and relevant Councillors would speak to Devon
County Council to see what could be done;
dd) MVV ran four EfW plants in the
UK, and an international figure would be provided outside of the
meeting as it was not available to hand during the
meeting;
ee) One advantage Germany had over
the UK was that a lot of infrastructure had been put in at the
beginning, whereas in the UK a lot was having to be put in
retrospectively, which was costly;
ff)
Plymouth City Council had signed off on a
delivery model for Heat Networks, with the first phase focusing on
the City Centre. Further phases would consider utilising heat from
the EfW and Medical Incinerator at Derriford;
gg)
MVV had not been consulted on the recent BBC article
on EfW plants;
i.
EfW plants were designed to be more beneficial than
landfill but still to get rid of waste;
ii.
The bigger issue was the high volumes of waste and
the need to decrease this at source;
iii.
The response sent to the BBC would be shared with
Committee members;
iv. Two people had contacted MVV since the article frustrated at the misconceptions, and the comments on the article online were largely positive too.
Supporting documents: