Agenda item
Central Park Petition - Response Report
Minutes:
Councillor Finn introduced the item and highlighted the following points:
a)
The Ponds Project was the most recent project to come forward as
part of the Central Park Improvement Plan;
b)
The Project was the third phase of the original Central Park
Project;
c)
The business case for the project was approved on 21 January 2022
and the aim was to transform water from a problem, to a
resource;
d)
The project involved re-landscaping the area of the park to provide
a nature-based solution to flooding using sustainable drainage
systems and to manage surface water and provide space for wildlife
and the public;
e)
The petition submitted, which ran from 16 July 2024 to 31 August
2024, raised four key issues.
Amanda Pannell
(petition author) added:
f)
The petition came about due to Plymouth City Council’s (PCC)
failure to communicate effectively and consider the needs of their
residents;
g)
Over 3000 park users and residents signed the ‘Fix Our
Park’ petition, and this would have been more but some
members of the public were not comfortable with sharing their
personal details;
h)
Regardless of Council Officers opinions and justifications for the
way they had communicated, 3000 people felt misinformed and
ignored;
i)
The public disputed some claims within the report, including that
the Ponds Project had featured a significant level of public
engagement before plans were finalised, and that a film was created
to ensure the public could visualise the final scheme;
j)
Only two of the 3000 members of the public who signed the petition
stated they had input on the plans, and that was due to their
membership to the now defunct ‘Friends of Central Park’
group;
k)
The film that was created to ensure the public could see what the
site would look like after the work was finished was not true to
what the park now looked like;
l)
There was genuine anger from members of the public about the lack
of information, and some blamed themselves for not taking the time
to investigate and challenge the plans before they took
place;
m)
From November 2022 to December 2023, park users were blocked from
using large areas of the park whilst witnessing felled trees,
enduring the noise from generators and heavy machinery and
experiencing detours through muddy, unlit diversions;
n)
Incorrect information was given regarding when paths would open up
again;
o)
From January 2024 no work was carried out for eight months, which
created stagnant water, fly tipping, unwelcoming signs and
overgrown paths;
p)
Members of the public lodged complaints online, over the phone and
spoke to both local Councillors and MPs;
q)
The public felt the petition was the only way to gain the
Council’s attention and create accountability for the work
done in the park;
r)
The petition authors had appreciated meeting with Council officers
within the park;
s)
Resurfacing of paths at Barn Park had started without public
warning which created confusion to regular users who could not
utilise their normal route to work or school;
t)
Members of the public would like to see recommendations from the
Housing and Community Services Scrutiny Panel to improve PCC
communication on the Pond Project.
Councillor Briars-Delve (Cabinet Member for Environment and Climate Change) added:
u)
The Central Park Improvement Project had been running since 2017
and was an example of cross party collaborative working, delivering
on a key proposal in the Joint Local Plan;
v)
The aim of the project was to re-landscape an area of Central Park
to provide a nature-based solution to flooding by using sustainable
urban drainage systems;
w)
It was fully accepted that at the time of the petition, the project
was not in a good state for various reasons, including the
contractors withdrawing from the site due to wet weather over the
winter and contractual issues meaning they did not
return;
x)
Since the petition had been submitted, the situation in park had
significantly improved and although the project was not finished,
the look and feel of the park was better;
y)
Fenced off areas had been removed as much as was possible whilst
the works continued;
z) The coming months would include the completion of pitch works, reinstatement the fields, further tree planting and landscaping works;
aa)
PCC accepted and apologised for delays in the scheme, and could
understand why the petition was launched;
bb)Public safety was at
the forefront of PCC’s responsibilities, however they could
not agree that an independent review would be advantageous or a
good use of public money as the progress of the project had
improved significantly since the petition was started.
In response to questions, it was explained:
cc)
The wider benefits of the project had been lost in the coverage of
the scheme due to the understandable concerns raised;
dd)The realities of
climate change had increased extreme rainfall and storm events, and
the project was an opportunity to improve flooding resilience in
that part of Plymouth;
ee)
This scheme, and other similar schemes, would have a positive
impact on the water quality in Plymouth Sound and there were
bio-diversity benefits that came with creating a wetland
habitat;
ff)
Southwest Water had recognised there was an issue with drainage at
Home Park Park and Ride whereby water
drained downhill and ended in the park;
gg)
Following the Water Quality Select Committee a Memorandum of
Understanding with Southwest Water had been created to enhance
future planning for the Home Park area. This meant that Central
Park was flagged as a key area to ensure additional water
didn’t flow there;
hh)One of the main
issues the public had raised was a lack of communication from the
Council, and it was suggested that monthly updates on the project
would be a valuable solution;
ii)
An online FAQ page had been set up and would be better
publicised;
jj)
Summer 2025 was the proposed end date to the project;
kk)
There were measures in place to address the communication issues
surrounding the project;
ll)
The key aspects to finish the project included land drainage on the
pitch field, including the field being topped and seeded, and the
main risk to this was the weather.
The Panel agreed to the following:
- To recommend developing a comprehensive communication plan to enhance communication for the park works project. This plan should include regular (at least monthly) updates via multiple channels, clear signage in affected areas, and an outline of the project plan so residents can understand the scheduled works and timelines;
- The project will be added to the Panel’s work programme for the 2025/26 Municipal Year.
Supporting documents:
-
241204 Scrutiny Report - Central Park Petition Response_, item 20.
PDF 224 KB
-
241204 Central Park Petition - Scrutiny Response Report FINAL, item 20.
PDF 313 KB