Agenda item
A38 Manadon Interchange scheme final business case development funding
Decision:
Councillor Stephens introduced the item.
Having considered all of the information including the information at item 15Cabinet:
1. Approved the Business Case attached to the report;
2. Allocated £12,808,832 for the project into the Capital Programme funded by:
· £8,897,042 ringfenced Department for Transport grant funding allocated specifically for this scheme.
· £3,911,790 un-ringfenced Integrated Transport Block grant funding that PCC is able to use to fund its transport priorities.
3. Authorised the procurement process set out in the report.
4. Delegated contract award decisions to the Service Director for Strategic Planning and Infrastructure where they do not already have authority to do so.
5. Instructs officers to work with the Cabinet Members for Planning and Infrastructure and Environment and Climate Change, in addition to relevant specialists from PCC’s Net Zero and Environmental Planning teams, to develop a comprehensive Climate Impact Assessment following the first consultation process to be reported to Cabinet prior to the next phase of consultation.
Minutes:
Councillor Stephens (Cabinet Member for Strategic Planning and Transport)introduced the item and highlighted the following points:
a)
60,000 vehicles a day
passed
through the A38 ManadonInterchange and it was the busiest junction in the City and was a pinch point on the
city’s road network;
i.
It was where the A386
connecting the city north to south, met the A38, connecting the
city east to west;
ii.
The A38
was
the only road on the strategic road network managed
by National Highways;
iii.
It was a
three-tier interchange, with the A38 running underneath, a
roundabout in the middle and a flyover carrying the A386 across the
top;
iv.
The junction was at the
confluence of the city’s growth areas as set out within the
joint local plan (JLP), and without additional capacity at Manadon,
future growth would be
constrained;
b) Derriford Hospital was undergoing a major redevelopment with a £140 million pound investment into its healthcare estate, with plans for future investment;
c)
The Ministry of Defence
(MoD) had announced a£4.4 billion
investment at
Devonport, demonstrating Plymouth’s
importance in defence of
the country;
d) The improvements to this interchange would complement other network improvements such as the Forder Valley Link Road, Derriford Hospital improvements and the Woolwell to the George transport scheme;
e) The interchange was part of the adopted statutory planning framework, the JLP identified the northern corridor as one of three priority growth areas to deliver regionally significant number of homes and jobs;
f)
The scheme
would also
include extensive walking and cycling provisions,
including;
i.
A new cycle bridge
across the A38;
ii.
A continuous 2-way
north/south cycle route;
iii.
Improved pedestrian
bridges;
iv.
Enhanced pedestrian
links to local areas of green
space;
v. New bus priority on Mannamead Road and at Crownhill;
g)
The impact of reducing
congestion on Manadonwould see an
overall reduction in carbon emissions
long-term;
h) The government’s large local majors program provided 85% of the funding for the Manadoninterchange;
i) The scheme had program entry status, meaning that it was within the Department for Transport’s national program of capital investments that it was committed to;
j) The decision for Cabinet was to consider the remainder of the development funding, which was £12.8 million pound, into the capital program to progress the scheme to final business case, as set out in the report;
k) Although the decision would provide authorisation to prepare the final business case, it did not provide authorisation to construct the scheme at this stage;
l) Delivering the final schemehad an estimated cost of £156.4 million;
m) Anticipated start for the scheme was considered to be Winter 2028;
n) If Cabinet decided to proceed, the project team would produce a detailed scheme design, progress the submission of a planning application and refine the land and buildings that need to be acquiredto allow construction;
o)
The decision
would
not give consent for third-party land purchases,
which would be the subject of a separate decision
at a later date;
p)
Councillors and officers
were keen to get the results back from the recent, extensive public
consultation to help guide work on the next phase of the
design;
q) Officers had been having positive discussions with potentially affected households and other stakeholders.
Councillor Briars-Delve (Cabinet Member for Environment and Climate Change) highlighted the following points aroundthe Climate Impact Assessment (CIA);
r) CIAs ensured that all projects that PCC led on considered eight different environmental aspects, bothin terms of net zero but also natural infrastructure also to improving transparency with the public and improving environmental outcomes;
s) It was his personal opinion that the CIA was not comprehensive.
In response to questions, supported by Paul Barnard (Service Director, Strategic Planning and Infrastructure), the following was discussed:
t)
The usual process with a
project of this nature was to make an allowance for any property
acquisitions that might be needed, but this was not part of the
decision being taken at this
time;
u)
The team always
preferred to secure a negotiated solution to property acquisition,
using compulsory purchase orders (CPOs) as a last
resort;
v) Frustration that local Councillors for the area had been misrepresenting the impact and scope of the scheme to local residents.
The Cabinetagreed to:
1.
Approve the Business
Case;
2.
Allocate
£12,808,832 for the project into the Capital Programme funded
by: £8,897,042 ringfenced
Department for Transport grant funding allocated
specifically for this scheme. £3,911,790
un-ringfenced Integrated Transport
Block grant funding that PCC was able to use to fund its transport
priorities;
3.
Authorise the
procurement process set out in the report;
4.
Delegate contract award
decisions to the Service Director for Strategic Planning and
Infrastructure, where they do not already have authority to do
so;
5. Instruct officers to work with Cabinet members for planning and infrastructure and environment and climate change, in addition to relevant specialists from PCC’s net zero and environmental planning teams, to develop a comprehensive climate impact assessment, following the first consultation process to be reported to Cabinet prior to the next phase of consultation.
Supporting documents:
-
A38 Manadon Interchange development to FBC Cabinet Committee Report July 2025 Final1.1a, item 7.
PDF 172 KB -
A 38 Manadon Interchange development to FBC Briefing-Report July 2025 Final1.0, item 7.
PDF 196 KB -
2025.06.25 A38 Manadon funding to FBC EqIA, item 7.
PDF 136 KB -
A38 Manadon FBC climate assessment, item 7.
PDF 161 KB
