Agenda item
MOUNT EDGCUMBE STORM REPAIRS PROGRESS REPORT
The Joint Committee will receive the Mount Edgcumbe Storm Repairs progress report.
Minutes:
The Strategic Director for Place submitted a progress report on the storm repairs which had affected a number of structures in the Park such as sea walls and quays. The report highlighted the following key areas –
the damage to the coastline had been extensive and had affected a number of structures; following the storms an initial assessment of the damage had been undertaken; |
||
|
|
|
(b)
|
following the assessment of the coastal damage, the damage had been broken down into four distinct areas of work which included – |
|
|
|
|
|
? |
Cremyll Quay – structure had now collapsed and required rebuilding; |
|
? |
Cremyll slipway – void appeared under the upper part of the slipway, works had not commenced; |
|
? |
Lower Lodge entrance sea wall – rebuilding of sections of the sea wall were required; |
|
? |
Battery Beach sea wall – sections of the wall had been compromised and required rebuilding and voids backfilled; |
|
|
|
(c)
|
the estimates provided for the works were in the region of £550,000; however, additional costs may be incurred to meet the requirements of the Marine Management Organisation and Natural England at an approximate total cost of £5,000; |
|
|
|
|
(d) |
an application had been made to the Environment Agency to try and secure funding towards the works at Cremyll Quay, Lower Lodge and Battery Beach; the works on the Cremyll slipway were outside of the scope of funding from the Environment Agency however, other funding streams were being investigated; |
|
|
|
|
(e) |
once confirmation of the level of funding from the Environment Agency had been received, work would be able to commence to secure the additional funding required; a programme of works had been drafted with a view to completing the works prior to winter. |
In response to questions raised by the Joint Committee, it was reported that –
(f) |
the Environment Agency were fully aware of the urgency of carrying out the repair works; |
|
|
|
|
(g) |
a delay in the commencement of the repair works would result in further erosion or storm damage; |
|
|
|
|
(h) |
the five options for the strengthening of the Cremyll Quay had been proposed by Cormac; |
|
|
|
|
(i) |
all the estimates for the repair works would be subject to stringent procurement processes; it was anticipated that this process would drive down costs; |
|
|
|
|
(j) |
following the successful securement of funding from the Environment Agency, it was anticipated that the various repair works would commence in September/October 2015; |
|
|
|
|
(k) |
officers undertook to contact the Ministry of Defence, regarding the tidal waves caused by the liberty boats using the estuary. |
Cornwall Council had received significant funding from the Environment Agency for repair works following damage caused by the storms; some of these schemes had been brought in under budget; the remaining monies had been allocated to prioritised schemes within the County; however, there was the potential for this scheme to be included within this process.
The Joint Committee agreed that –
when the level of Environment Agency grant funding is known, the Park Manager prepares a business case for funding the residual cost through a capital scheme to be considered by Plymouth City Council’s Cabinet for inclusion in the City Council’s capital programme; |
|||
|
|
||
(2) |
a similar business case is put to Cornwall Council for 50% match funding as its contribution. |
||
The Joint Committee also noted the report.
Supporting documents:
- JC Report 17.07.15 M E storm repairs, item 8. PDF 70 KB
- Strengthening Options - storm damage, item 8. PDF 551 KB