Agenda item

Contract and facility performance and current status

Members will receive a presentation from Mark Turner (SWDWP Project Director/Contract Manager) and Martyn Stapleton (SWDWP Assistant Contract Manager) providing a project update summarising the performance of the contract and facility for 2015/16 and its current status.

Minutes:

Mark Turner (SWDWP Contract Manager), Martyn Stapleton (SWDWP Assistant Contract Manager) and Simon Arthurs (Senior Financial Analyst) provided members with details of the SWDWP contract, facility performance for the first year of operation and current status. 

 

The highlights of the presentation included –

 

(a)

contract and facility performance 2015/16, contract year 1 key dates –

 

·         11 September 2015 - full service commencement certified;

·         15 October 2015 – steam exported to MOD;

 

(b)

MVV contract and facility performance 2015/16 (part year) -

 

·         MVV achieved 99.99% diversion from landfill (vs 97% target);

·         EfW maximum net plant efficiency 49.7% (vs 48.8% expected);

·         increased carbon savings 76,773 tCO2/year (vs 73, 594 tCO2/year);

·         plant availability – 91% with 6 unplanned shutdowns;

·         21 performance indicator breaches (mainly involving turnaround times);

 

(c)

SWDWP contract performance 2015/16 –

 

·         project won 2 more awards in 2015/16 (9 now in total) – best national Public Sector award for Decentralised Energy and best Market Development award in Europe for Combined Heat and Power;

·         SWDWP total waste tonnage delivered was 1.0% down on forecast and 3.2% below contract waste profile (established 2009);

·         Defra Waste Infrastructure Grant (PFI) received from April 2015;

 

(d)

SWDWP tonnages and budgets 2015/16 –

 

·         tonnage delivered 1,500 tonnes below forecast for 2015/16 (May 2015 – May 2016);

·         expenditure within budget (which includes all costs – contract management, business rates, S106 contributions, pass-throughs);

·         final 2015/16 financial reconciliation to be agreed with MVV;

 

(e)

community communications 2015/16 summary –

 

·         18 media stories;

·         76 complaints (54 of which related to odour);

·         25 enquiries (several of which related to ‘smoke’ emanating from the stack – which was in fact steam);

·         22 compliments;

·         3 Liaison Group meetings (the meetings are well supported, positively engaged and collaborative);

·         zero formal consent breaches;

 

(f)

EfW community area summary –

 

·         many site visits and tours have taken place with technical and resident groups;

·         SWDWP partners are utilising the facility and the Community Liaison Manager;

·         leaflets/flyers have been produced to promote the visitor centre and site tours;

·         school visits (ranging from Year 1 – Year 12) have increased via word of mouth (schools have not yet been formally targeted);

 

(g)

2016/17 contract update and current status –

 

·         MVV have been achieving 99.99% diversion from landfill (vs 97% target);

·         the annual three week planned maintenance shutdown has been completed;

·         there has been one unplanned shutdown to date (caused by a large tree trunk blocking the ash shute);

·         there have been 68 complaints since April 2016 (64 of which related to odour - 50 related to odour during the June shutdown);

·         a small number of local residents complain on a regular basis;

 

(h)

odour issues during the annual shutdown –

 

·         a formal breach was issued from the Environment Agency for poor control of odour as a result of the annual shutdown (the shutdown fan odour control filter did not meet its life expectancy);

·         a petition was received in July from 200 local residents regarding the odour experienced during the annual shutdown;

·         MVV have written to local residents to apologise for the situation and to explain the action being taken to improve the situation;

·         MVV are currently investigating the problem with the shutdown fan and exploring alternative solutions;

·         MVV are planning to move the annual shutdown to September 2017 when it is hoped there will be less disruption;

 

(i)

Partnership waste deliveries – 2016/17 to date –

 

·         tonnage deliveries have been very reliable and slightly above target;

·         forecast figures have been very accurate so far; 

·         the figures are measured as a partnership;

·         contract waste is slightly higher than predicted;

 

(j)

community area summary – April – July 2016 –

 

·         the community area is available five days a week;

·         two events can happen at the same time due to the space and facilities available;

·         currently only Plymouth schools visit the facility, other schools will be targeted as soon as possible;

 

(k)

community communications April – August 2016 summary –

 

·         5 media stories;

·         68 complaints (64 of which related to odour);

·         7 enquiries;

·         9 compliments;

·         1 Liaison Group meeting (the meetings are well supported, positively engaged and collaborative);

·         zero formal consent breaches;

 

(l)

EfW formal opening ceremony and Prince of Wales technical visit –

 

·         the EfW facility was officially opened by Councillor Roger Croad on 9 July 2016;

·         the opening was attended by representatives from MVV, the MOD and partner agencies;

·         Prince Charles has visited the facility and received a tour of the plant.