Agenda item
CONTRACT AND FACILITY PERFORMANCE AND CURRENT STATUS
To receive a presentation summarising the performance of the contract and facility for 2017/18 and its current status.
Minutes:
Martyn Stapleton (SWDWP Assistant Contract Manager) and Ashleigh Sherrell (SWDWP Project Co-ordinator) provided members with details of the SWFWP annual performance summary and project update.
The highlight of the presentation included –
(a) SWDWP Overview of 2017/18
· EfW facility has been fully operational for nearly 3 years;
· MVV’s overall 2017/18 service and performance was good;
· Service issues had been minor in nature and we continue to work to reduce areas of difference in contract delivery;
· MVV & SWDWP continue to work proactively with collection teams to optimise Partnership deliveries and waste composition;
· MVV have complied with planning and environmental permit conditions with five exceptions;
· Planned outage in September 2017 was successful. Odour issues were minimal (but 2018 outage has had some issues);
· Defra confirmed SWDWP compliant with PFI grant conditions.
(b) MVV Contract and Facility Performance 2017/18 Summary
· MVV achieved 99.96% diversion from landfill (vrs 97% target);
· Carbon savings of 78,400 tCO2/year (vrs 73,594 tCO2/year expected);
· Plant availability 91% (90% target) with 14 unplanned shutdowns;
· 5 exceedances of Environmental Permit: (Odour, late report submission & CO2 emission breach);
· 33 Performance Indicator breaches;
· 28 vehicle turn-around times (0.2%);
· 3 non-adherences to Waste Acceptance Protocol;
· 2 maintenance tasks not undertaken to time;
· Annual waste throughput 9,412 tonnes above the design point of 245,000 tonnes.
(c) SWDWP Tonnages and Budgets 2017/18
· SWDWP original forecast given to MVV for 2017/18 = 167,985 (revised forecast of 164,744 following update to PCC tonnages);
· SWDWP 2.21% below revised tonnage forecast (4.1% below original forecast);
· SWDWP total budget expenditure 1.0% below forecast.
|
Plymouth |
Torbay |
Devon |
SWDWP |
Contract Tonnage profile |
81,624 |
28,802 |
61,174 |
171,600 |
Forecast Tonnage |
75,740 |
36,700 |
52,304 |
164,744 |
Actual Tonnage |
76,639 |
35,672 |
48,788 |
161,099 |
Forecast Budget |
£7.80m |
£3.60m |
£5.51m |
£16.91m |
Actual Out Turn Expenditure |
£7.71m |
£3.45m |
£5.41m |
£16.57m |
Defra WIG (PFI grant) |
£3.39m |
£1.19m |
£2.55 |
£7.14m |
(d) 2018/19 Contract Update and Current Status
· MVV achieving 100% diversion from landfill (versus 97% target);
· Major annual shutdown from 5th – 27th June;
· With the exception of the planned outage, MVV reported only 1 hour and 43 minutes in lost availability (due to a reset on the ID fan);
· 3 Performance Indicator breaches (all turn-around times);
· 33 complaints received during the June outage;
· 2 permit breaches; 1 of these relating to the odour event;
· SWDWP total tonnage delivered (to 30 June) 1.99% above forecast;
(e) Partnership Waste Deliveries – 2018/19 to date (Apr – Jun);
|
Total tonnage to date |
Plymouth Forecast |
19,084 |
Plymouth Actual |
19,965 |
Torbay Forecast |
9,303 |
Torbay Actual |
9,152 |
Devon Forecast |
13,458 |
Devon Actual |
13,562 |
SWDWP Forecast |
41,845 |
SWDWP Actual |
42,679 |
(f) Annual Outage Highlights – June 2018
· 5th - 27th June official downtime (plant went back online a week ahead of schedule);
· Increased complaints;
· Waste bunker at 85% (11,000 tonnes) by the end of the outage, MVV ran the bunker down to 9% in preparation;
· All major works completed successfully including refractory and grate bar replacement, repairs to economiser 3, de-slagger chute replacement, crane maintenance, works on the turbine gearbox and a complete overhaul of the conveying system (de-slaggers, ash and residue conveyors and bucket elevators).
(g) Odour issues during the 2018/19 Annual Shutdown
· 33 complaints received between 5th and 27th June during the planned shutdown;
· One resident alone contributed to half of the above, complaining a total of 16 times;
· The EA and PCC planning officers visited site to investigate;
· Genuine odour event occurred during the last week in shut-down leading to complaints from multiple sources;
· MVV submitted a Schedule 5 notification to the EA.
(h) Community Communications April – June 2018 Summary
Media |
1 (1 Newspaper article) |
One Plymouth Herald report on MVV ‘clean the creek’ event which highlighted the vandalism in Blackie Woods. |
Complaints |
33 |
33 complaints reported during the June outage (30 relating to odour and 3 relating to noise reports). |
Enquiries |
0(via email / telephone) |
No enquiries. |
Compliments |
9 |
Positive comments and thanks received in response to site visits |
Liaison Groups |
0 |
Incinerator Liaison Committee meeting moved to 6 monthly – next meeting in July. |
Formal-Consent Breaches |
1 |
Schedule 5 notification submitted to the EA in June for the odour event. |