Agenda item

CONTRACT AND FACILITY PERFORMANCE AND CURRENT STATUS

To receive a presentation summarising the performance of the contract and facility for 2017/18 and its current status.

 

Minutes:

Martyn Stapleton (SWDWP Assistant Contract Manager) and Ashleigh Sherrell (SWDWP Project Co-ordinator) provided members with details of the SWFWP annual performance summary and project update.

 

The highlight of the presentation included –

 

(a)   SWDWP Overview of 2017/18

·         EfW facility has been fully operational for nearly 3 years;

·         MVV’s overall 2017/18 service and performance was good;

·         Service issues had been minor in nature and we continue to work to reduce areas of difference in contract delivery;

·         MVV & SWDWP continue to work proactively with collection teams to optimise Partnership deliveries and waste composition;

·         MVV have complied with planning and environmental permit conditions with five exceptions;

·         Planned outage in September 2017 was successful. Odour issues were minimal (but 2018 outage has had some issues);

·         Defra confirmed SWDWP compliant with PFI grant conditions.

 

(b)  MVV Contract and Facility Performance 2017/18 Summary

·         MVV achieved 99.96% diversion from landfill (vrs 97% target);

·         Carbon savings of 78,400 tCO2/year (vrs 73,594 tCO2/year expected);

·         Plant availability 91% (90% target) with 14 unplanned shutdowns;

·         5 exceedances of Environmental Permit: (Odour, late report submission & CO2 emission breach);

·         33 Performance Indicator breaches;

·         28 vehicle turn-around times (0.2%);

·         3 non-adherences to Waste Acceptance Protocol;

·         2 maintenance tasks not undertaken to time;

·         Annual waste throughput 9,412 tonnes above the design point of 245,000 tonnes.

 

(c)   SWDWP Tonnages and Budgets 2017/18

·         SWDWP original forecast given to MVV for 2017/18 = 167,985 (revised forecast of 164,744 following update to PCC tonnages);

·         SWDWP 2.21% below revised tonnage forecast (4.1% below original forecast);

·         SWDWP total budget expenditure 1.0% below forecast.

 

 

Plymouth

Torbay

Devon

SWDWP

Contract Tonnage profile

81,624

28,802

61,174

171,600

Forecast Tonnage

75,740

36,700

52,304

164,744

Actual Tonnage

76,639

35,672

48,788

161,099

Forecast Budget

£7.80m

£3.60m

£5.51m

£16.91m

Actual Out Turn Expenditure

£7.71m

£3.45m

£5.41m

£16.57m

Defra WIG (PFI grant)

£3.39m

£1.19m

£2.55

£7.14m

 

 

(d)  2018/19 Contract Update and Current Status

·         MVV achieving 100% diversion from landfill (versus 97% target);

·         Major annual shutdown from 5th – 27th June;

·         With the exception of the planned outage, MVV reported only 1 hour and 43 minutes in lost availability (due to a reset on the ID fan);

·         3 Performance Indicator breaches (all turn-around times);

·         33 complaints received during the June outage;

·         2 permit breaches; 1 of these relating to the odour event;

·         SWDWP total tonnage delivered (to 30 June) 1.99% above forecast;

 

(e)  Partnership Waste Deliveries – 2018/19 to date (Apr – Jun);

 

 

Total tonnage to date

Plymouth Forecast

19,084

Plymouth Actual

19,965

Torbay Forecast

9,303

Torbay   Actual

9,152

Devon Forecast

13,458

Devon   Actual

13,562

SWDWP Forecast

41,845

SWDWP Actual

42,679

 

 

(f)    Annual Outage Highlights – June 2018

·         5th - 27th June official downtime (plant went back online a week ahead of schedule);

·         Increased complaints;

·         Waste bunker at 85% (11,000 tonnes) by the end of the outage, MVV ran the bunker down to 9% in preparation;

·         All major works completed successfully including refractory and grate bar replacement, repairs to economiser 3, de-slagger chute replacement, crane maintenance, works on the turbine gearbox and a complete overhaul of the conveying system (de-slaggers, ash and residue conveyors and bucket elevators).

 

(g)   Odour issues during the 2018/19 Annual Shutdown

·         33 complaints received between 5th and 27th June during the planned shutdown;

·         One resident alone contributed to half of the above, complaining a total of 16 times;

·         The EA and PCC planning officers visited site to investigate;

·         Genuine odour event occurred during the last week in shut-down leading to complaints from multiple sources;

·         MVV submitted a Schedule 5 notification to the EA.

 

(h)  Community Communications April – June 2018 Summary

 

Media

1 (1 Newspaper article)

One Plymouth Herald report on MVV ‘clean the creek’ event which highlighted the vandalism in Blackie Woods.

Complaints

33

33 complaints reported during the June outage (30 relating to odour and 3 relating to noise reports).

Enquiries

0(via email / telephone)

No enquiries.

Compliments

9

Positive comments and thanks received in response to site visits

Liaison Groups

0

Incinerator Liaison Committee meeting moved to 6 monthly – next meeting in July.

Formal-Consent Breaches

1

Schedule 5 notification submitted to the EA in June for the odour event.