Better Places Programme: Armada Way Scheme
11/09/2024 - L13 24/25 - The Transformation of Armada Way
10/09/2024 - The Transformation of Armada Way
Cabinet:
1. Approved the final construction cost for the approved Armada Way design as £29,892,665;
2. Recommended the Leader approves additions to the Capital Programme as set out in the report giving a maximum spend allocation of £29,892,665 to finance the construction of the approved Armada Way scheme;
3. Noted that to support the on-going maintenance of projects within the city centre for a period of five years starting in 2025/2026 that hard and soft landscaping maintenance be funded from previously identified capital approved resources already forming part of the Capital Programme;
4. Granted authority to the Service Director for Strategic Planning and Infrastructure to take all such action as necessary to implement the project including all subsequent design amendments (excluding amendments which impact on the retention of any existing trees or the approved translocation of trees), scheme approval submissions, procurement and contract awards associated with developing and delivering the Armada Way scheme through to construction and completion, in consultation with the relevant Cabinet Members;
5. Delegated to the Cabinet Member for Finance authority to make any decisions which impact on the retention of any existing trees, or the approved translocation of trees associated with developing and delivering the Armada Way scheme through to construction and completion.