A38 Manadon Interchange scheme final business case development funding
Meeting: 07/07/2025 - Cabinet (Item 7)
7 A38 Manadon Interchange scheme final business case development funding
PDF 172 KB
Additional documents:
- A 38 Manadon Interchange development to FBC Briefing-Report July 2025 Final1.0, item 7
PDF 196 KB
- 2025.06.25 A38 Manadon funding to FBC EqIA, item 7
PDF 136 KB
- A38 Manadon FBC climate assessment, item 7
PDF 161 KB
Decision:
Councillor Stephens introduced the item.
Having considered all of the information including the information at item 15Cabinet:
1. Approved the Business Case attached to the report;
2. Allocated £12,808,832 for the project into the Capital Programme funded by:
· £8,897,042 ringfenced Department for Transport grant funding allocated specifically for this scheme.
· £3,911,790 un-ringfenced Integrated Transport Block grant funding that PCC is able to use to fund its transport priorities.
3. Authorised the procurement process set out in the report.
4. Delegated contract award decisions to the Service Director for Strategic Planning and Infrastructure where they do not already have authority to do so.
5. Instructs officers to work with the Cabinet Members for Planning and Infrastructure and Environment and Climate Change, in addition to relevant specialists from PCC’s Net Zero and Environmental Planning teams, to develop a comprehensive Climate Impact Assessment following the first consultation process to be reported to Cabinet prior to the next phase of consultation.
Minutes:
Councillor Stephens (Cabinet Member for Strategic Planning and Transport)introduced the item and highlighted the following points:
a)
60,000 vehicles a day
passed
through the A38 ManadonInterchange and it was the busiest junction in the City and was a pinch point on the
city’s road network;
i.
It was where the A386
connecting the city north to south, met the A38, connecting the
city east to west;
ii.
The A38
was
the only road on the strategic road network managed
by National Highways;
iii.
It was a
three-tier interchange, with the A38 running underneath, a
roundabout in the middle and a flyover carrying the A386 across the
top;
iv.
The junction was at the
confluence of the city’s growth areas as set out within the
joint local plan (JLP), and without additional capacity at Manadon,
future growth would be
constrained;
b) Derriford Hospital was undergoing a major redevelopment with a £140 million pound investment into its healthcare estate, with plans for future investment;
c)
The Ministry of Defence
(MoD) had announced a£4.4 billion
investment at
Devonport, demonstrating Plymouth’s
importance in defence of
the country;
d) The improvements to this interchange would complement other network improvements such as the Forder Valley Link Road, Derriford Hospital improvements and the Woolwell to the George transport scheme;
e) The interchange was part of the adopted statutory planning framework, the JLP identified the northern corridor as one of three priority growth areas to deliver regionally significant number of homes and jobs;
f)
The scheme
would also
include extensive walking and cycling provisions,
including;
i.
A new cycle bridge
across the A38;
ii.
A continuous 2-way
north/south cycle route;
iii.
Improved pedestrian
bridges;
iv.
Enhanced pedestrian
links to local areas of green
space;
v. New bus priority on Mannamead Road and at Crownhill;
g)
The impact of reducing
congestion on Manadonwould see an
overall reduction in carbon emissions
long-term;
h) The government’s large local majors program provided 85% of the funding for the Manadoninterchange;
i) The scheme had program entry status, meaning that it was within the Department for Transport’s national program of capital investments that it was committed to;
j) The decision for Cabinet was to consider the remainder of the development funding, which was £12.8 million pound, into the capital program to progress the scheme to final business case, as set out in the report;
k) Although the decision would provide authorisation to prepare the final business case, it did not provide authorisation to construct the scheme at this stage;
l) Delivering the final schemehad an estimated cost of £156.4 million;
m) Anticipated start for the scheme was considered to be Winter 2028;
n) If Cabinet decided to proceed, the project team would produce a detailed scheme design, progress the submission of a planning application and refine the land and buildings that need to be acquired ... view the full minutes text for item 7