Agenda and draft minutes
Venue: Warspite Room, Council House. View directions
Contact: Hannah Chandler-Whiting Email: democraticsupport@plymouth.gov.uk
No. | Item |
---|---|
APPOINTMENT OF CHAIR AND VICE CHAIR In accordance with the Joint Working Agreement a new Chair will be elected from Plymouth City Council’s Committee members.
The new Chair will invite nominations for a new Committee Vice-Chair in accordance with the Joint Working Agreement and a new Vice-Chair will be elected from Devon County Council’s Committee members. Minutes: The Committee agreed the appoint Councillor Tom-Briars Delve as Chair and Councillor Roger Croad as Vice Chair for the meeting. |
|
DECLARATIONS OF INTEREST Members will be asked to make any declarations of interest in respect of items on this agenda. Minutes: No declarations of interest were made. |
|
To sign and confirm as a correct record the minutes of the meeting held on 19 October 2023.
Minutes: The Committee agreed the minutes of the meeting held on 19 October 2023 as an accurate record. |
|
CHAIR'S URGENT BUSINESS To receive reports on business which, in the opinion of the Chair, should be brought forward for urgent consideration. Minutes: There were no items of Chair’s urgent business. |
|
CONTRACTOR UPDATE ON FACILITY PERFORMANCE, COMMUNITY INTERFACE AND UK BUSINESS To receive a presentation from Mike Turner; MVV Managing Director and Jade Beavan; MVV Community Liaison Manager summarising the performance of the contract, facility and MVV’s business performance.
Additional documents: Minutes: Mike Turner (MVV Managing Director) provided an update and highlighted the following for 2023/24:
a)
2023/24 had been a positive year overall with
greater than designed availability, increased carbon savings and
minimal public complaints; b)
The summer 2023 open day has resulted in over 2000
visitors on site; c)
Some long outages had affected throughput, but
overall had been a good year for availability so the electricity
generated and heat exported had been as high as they could
be; d)
The heat exported had been lower than previous years
due to a health and safety issues with the heating system at the
dockyard; e)
Availability was very good and above national
average; f)
CO2eq saving was 92,547 tonnes, higher
than the previous three years and above target; g)
There had been less unplanned shutdowns than in the
previous years, two due to tube leaks and one relating to a grate
fault; h)
There had been one justified complaint in 2023/24
and was due to gas monitors being triggered during works and vents
automatically opening;
i.
Two further complaints had been attributed to other
facilities; i)
Waste diversion was above target at
99.99%; j)
Performance deductions had been applied;
i.
There were breaches in relation to delivery
turnaround times of 0.1%;
ii.
There had been 279 breaches in relation to waste
acceptance protocol due to human error
when initially inputting a registration and mistaking the letter X
for the letter K, which then went unnoticed. ANPR is being
installed to remove the risk of errors like this in
future;
iii.
One complaint had not been logged within timeframe,
and one outage had not been reported within timeframe; k)
Signage upgrades to incorporate the new logo and
changed to PPE (Mandatory eye protection introduced); l)
A new ladder inspection regime had been
introduced; m)
New fire hose reels had been fitted and the fire
system had been upgraded; n) The Cardox online high pressured blockage cleaning system had been introduced under trial.
Jade Beavan (MVV Community Liaison Manager) added the following in relation to community engagement:
o)
Reinforcement of the waste hierarchy and supported
delivery of Partner Council’s key waste minimisation
messages; p)
Facilitated tours and careers Q&A
sessions; q)
Organised and attended local events; r)
Participated in waste education meetings and hosted
partner site tours and waste education visits; s)
The decrease in hours spent with schools was likely
due to the cost of transport for schools to get to the
facility; t)
Outreach offerings had increased; u)
Usage of visitor centre had increased, particularly
with Plymouth schools, which Jade had been working hard
on; v)
There had not been any interest in virtual tours
since the conclusion of the COVID19 pandemic; w)
The open day in 2023 had seen very high visitor
numbers at approximiately 2000, and whilst 2024 was lower at 350,
it was more manageable;
i.
All Council partners had attended the
event;
ii.
Interest in bookings had increased after the
event. Mike Turner (MVV Managing ... view the full minutes text for item 34. |
|
CURRENT STATUS OF CONTRACT AND FACILITY PERFORMANCE To receive an update on the current status of the contract and facility for 2024/25 from the SWDWP Contract Team.
Additional documents: Minutes: Ashleigh Sherrell (Contract Manager, SWDWP) highlighted the following points in her presentation on The MVV and Facility performance in 2024/25:
a)
An interim outage was conducted between 8–17 May 2024
totalling 270 hours of work, including replacement of 120 grate
bars, repairing leaks in the Economiser and installing a new chain
in the bucket elevator; b)
There was a major outage due in 2025, with the turbine to be
removed for an overhaul meaning the plant would not generate energy
for up to eight weeks; c)
There had been six Performance Failures for minor operational
matters surrounding vehicle deliveries and waste
acceptance; d)
MVV had been identifying and making improvements to its safe work
procedures within the tipping hall; e)
Parties were working together to put in place an effective
Contingency Plan in the rare event that diversion from the Facility
would be required; f) The partnership was 2.3% below forecast waste tonnage at the time of the meeting.
Mel Hayward (Assistant Contract Manager, SWDWP) added:
g)
There had been two noise complaints reported, one which was
confirmed and caused by a bearing failure on the bucket elevator,
the other was investigated but no noise was found;
h)
There has been two media enquiries, one in conjuction with Devon
County Council in relation to waste segregation for POPs
legislation, and another in relation to the recent BBC article on
increased emissions of greenhouse gases from
incinerators;
i)
One Liaison Group meeting had been organised but there had been no
interest/attendance from local residents and whilst this was
positive in that they didn’t want to meet to discuss anything
negative, the team were going to organise another before the end of
the year aiming for good attendance to continue good community
engagement;
j)
There had been two consent breaches with time exceedances on
CO2 and TOC emissions due to a plant trip in June 2024,
and Section 5 notices were issued to the Environment Agency, as
required; k) There had been 12 school bookings made across the partnership from April-September 2024.
In response to questions it was discussed further:
l)
That Devon County Council would book 10 slots for schools for the
year, but there had been some issues with some
cancellations;
m)
A copy of the presentation would be shared with Committee
Members; n) The turbine would be carefully transported to Newcastle for works.
|
|
DATE AND LOCATION OF NEXT MEETING The note that the next meeting is scheduled for 16 October 2025 at Council House, Plymouth.
Minutes: The Committee agreed to note 16 October 2025 as the date for the next meeting, to be held at Council House, Plymouth. |
|
EXEMPT BUSINESS To consider passing a resolution under Section 100A(4) of the Local Government Act 1972 to exclude the press and public from the meeting for the following item(s) of business on the grounds that it (they) involve the likely disclosure of exempt information as defined in paragraph 3 of Part 1 of Schedule 12A of the Act, as amended by the Freedom of Information Act 2000. Minutes: The Committee agreed to pass a resolution under Section 100A(4) of the Local Government Act 1972 to exclude the press and public from the meeting for the following item(s) of business on the grounds that it (they) involve the likely disclosure of exempt information as defined in paragraph 3 of Part 1 of Schedule 12A of the Act, as amended by the Freedom of Information Act 2000. |
|
COMMERCIAL CONTRACT PERFORMANCE AND ISSUES / SOUTH WEST DEVON WASTE PARTNERSHIP ACCOUNTS Members will receive a presentation from Ashleigh Sherrell; SWDWP Contract Manager summarising the contract’s commercial performance, and any issues faced for contract year 2023/24 and the partnership’s budget forecast and allocations for 2024/25. Minutes: Ashleigh Sherrell (Contract Manager, SWDWP) provided an update on the contract’s commercial performance, and any issues faced for contract year 2023/24 and the partnership’s budget forecast and allocations for 2024/25. |
|
ANY OTHER BUSINESS Minutes: Thanks was given to Councillors Hart and Croad for their involvement in the project, as they would be stepping down from their roles as Councillors in 2025. |